When you install solar panels, it affects the flow of electricity in your local electricity network. In addition, your system may feed some surplus electricity back into the grid. Therefore, your local DNO must have certain information about the installation.
The DNO manages the local electricity network serving your property. It checks whether your solar system can safely connect to that network. This process is called a DNO Solar Panel Application. Small systems may only need a G98 notification.
Larger systems usually require a G99 application before your solar panel installation process. Battery storage can also affect your DNO connection requirements. This guide explains G98, G99, G100, approval, export limits, and DNO letters. It also explains what happens after you submit a DNO application.
What Is a DNO?
DNO stands for the Distribution Network Operator. Your DNO manages the distribution network in your region. It takes care of the local electricity cables, substations, and other pieces of network equipment. Your electricity supplier is not your DNO. Your electricity supplier supplies the electricity to you and handles your tariff.
Your DNO manages the physical electricity network. Your DNO depends on your property’s geographic area. You can find it using your postcode and electricity bill. The Energy Networks Association provides a postcode checking service.
Do I Need a DNO Application for Solar Panels?
Yes, in almost all grid-connected solar installations. The important question concerns the type of DNO process required. Small systems may qualify for G98 notification. Larger systems normally require a G99 application.
Your installer should check this before he installs the solar panels. This includes cases where the installation is done mainly for self-consumption. Your solar PV system can still potentially export electricity. Therefore, the DNO needs information about the proposed connection.
The same principle can apply to battery storage. A battery may export electricity through its inverter. Your installer should assess your complete solar and battery system.
Why Is a DNO Solar Application Required?
Solar panels generate electricity at your property. After that, the inverter turns this electricity into AC electricity. Some electricity may then flow into the local grid. This process is called export.
Export can affect voltage and power flows across the network. It can also affect local transformers and electricity cables. The DNO must therefore assess the proposed grid connection. This helps protect your property and other network users.
The DNO considers potential worst-case export conditions. This includes periods when several systems export simultaneously. The aim is a safe and stable electricity distribution network.
Your Roof Could Be Saving You Money
£0 Upfront Finance Available
25-Year Panel Warranty
Free Quote, No Obligation
GOOD
Based on 277 reviews
Posted on Google![]()
Lawrence SetchellTrustindex verifies that the original source of the review is Google.
Great and friendly service, from the office to the engineers. Very hassle free and quick servicePosted on Google![]()
teresa nowersTrustindex verifies that the original source of the review is Google.
Excellent service, helpful and polte. Hard working too.Posted on Google![]()
Laura O'NeillTrustindex verifies that the original source of the review is Google.
Fantastic service by all the team involved.Posted on Google![]()
jenny marshall-foxTrustindex verifies that the original source of the review is Google.
My boiler broke down and within two weeks a new one fitted very quick service, three men came at 11am and stayed late until finished and working, they had a lot of problems that were unexpected but worked well and were very clean workers, and polite, I would recommend to anyone.Posted on Google![]()
Sarah MansfieldTrustindex verifies that the original source of the review is Google.
Highly recommended, surveyors did a brilliant job ,they came out on a Saturday, paperwork completed by Wednesday and jobs booked in for thu and Fri this week ,I'm so pleased first team arrived on time did loft insulation on our loft , extractor fans in 3 bathrooms and our kitchen , and fitted trickle vents to all windows ,did a great job ,friendly ,polite and got the job done .on Friday the combi boiler guys arrived ,smart h and p solutions limited ,and they did a fantastic job, lovely friendly polite guys done a professional job went above and beyond ,removal of a very old broken system, replaced all pipe works and installed new combi boiler system, and fitted smart valves on all radiators ,left everything clean And tidy and covered stairs flooring etc ,done a fantastic job and the house is lovely and warm ,I can't recommend them enough, they really have done such a lovely job .highly recommended the process has been so quick and everyone involved have done a great job .thank you all .
What Does the DNO Look At?
The DNO mainly considers your system’s electrical characteristics. The inverter rating is particularly important. It determines the potential output reaching your electrical connection. The DNO may also consider your export capacity.
Other important information can include:
- Inverter make and model
- Inverter power output
- Total generation capacity
- Battery storage capacity
- Single-phase or three-phase connection
- Existing generation at the property
- Proposed export limitation
- Grid connection details
- Electrical protection arrangements
- Local network capacity
The DNO may also consider available network capacity. Your installer provides the technical information. You normally do not need to prepare these documents yourself.
What Does the DNO Not Usually Need?
The DNO does not mainly assess your annual electricity spending. Your number of bedrooms is also not the key factor. The number of solar panels alone does not determine approval.
Your roof space can affect system design. However, roof size does not decide the DNO process. Your electricity supplier does not give the grid connection approval either. This responsibility goes to your local DNO.
What Information Does the DNO Need?
The DNO focuses on electrical network impact. The inverter and export capability are particularly important. Your installer usually prepares the required technical information.
This can include:
- Inverter make and model
- Inverter rated power
- Total generation capacity
- Battery details
- Single-phase or three-phase connection
- Grid connection point
- Property location
- Electrical layout
- Wiring diagram
- Protection details
- Installer certification details
The exact information depends on the application. A G99 application can require more technical information. Your installer should complete the relevant forms.
G98 vs G99: What Is the Difference?
G98 and G99 are engineering requirements for connecting generation. They apply to different types and sizes of generating systems. The commonly used G98 limit is 16A per phase. At 230V, this equals approximately 3.68kW per phase.
G98 generally covers smaller compliant generating systems. G99 applies when systems fall outside the G98 conditions.
Here is a simpler comparison:
| Feature | G98 | G99 |
|---|---|---|
| Typical system | Smaller solar PV systems | Larger or more complex systems |
| Common threshold | Up to 16A per phase | Above G98 limits |
| Approximate single-phase limit | 3.68kW | Above 3.68kW |
| DNO process | Notification after commissioning | Application before installation |
| Prior approval | Usually not required | Usually required |
| Typical users | Domestic solar | Large domestic and commercial solar |
| Installer involvement | Installer submits notification | Installer submits application |
| Network assessment | Simpler | More detailed |
| Export restrictions | May apply | May apply |
| Timescale | Usually shorter | Can take longer |
Important: The thresholds for three-phase connections differ. The exact conditions can also depend on your equipment. Always ask your installer which process applies to you.
What Is G98 for Solar Panels?
G98 covers certain smaller generating installations. Many standard domestic solar PV systems can qualify. The commonly used limit is 16A per phase. For a 230V single-phase supply, this equals about 3.68kW.
The installer normally does not need prior DNO approval. Instead, the installer notifies the DNO after commissioning. The current G98 process requires timely notification. Your installer should handle this as part of the full solar system installation process. G98 can therefore make smaller solar projects much simpler.
What Is G99 for Solar Panels?
G99 covers generating systems outside the G98 process. This can include larger solar PV systems. It can also include certain battery storage systems. The DNO normally needs to approve the connection first.
Your installer submits the G99 application to your DNO. The DNO then assesses the proposed solar project. It may approve the requested system without changes. It may impose an export limitation. It may also request network reinforcement works. Your installer should explain the final connection requirements.
What Is G100?
G100 relates to export limitation arrangements. An export limitation controls the electricity sent to the grid. For example, your inverter could support 10kW output. The DNO could allow only 5kW of grid export.
A suitable export limitation system can enforce that restriction. This can help when the local grid has limited capacity. Your installer may need to follow G100 requirements. The DNO will confirm whether an export limitation is required.
What Happens After a DNO Application?
The DNO assesses your proposed grid connection. It then provides an outcome or connection offer. The result depends on your local electricity network. There are several possible outcomes.
1. Your Application Is Accepted
The DNO may accept your requested system capacity. This means the network can support the proposed connection. You can then proceed with the approved installation.
No network reinforcement may be required. Your installer should follow the approved technical requirements. This is the simplest possible outcome.
2. The DNO Requires Export Limitation
The DNO may restrict how much electricity you export. This can happen when the local network has limited capacity. Your solar system may still be installed at its proposed size. However, the grid export must remain within the approved limit.
A compliant export control system may be required. The DNO may also require testing or witnessing. Any associated fee depends on the DNO and project. Your installer should explain these requirements before installation.
3. The Electricity Supply Needs Upgrading
Sometimes the existing connection cannot support the proposed system. The DNO may require a supply upgrade. This could involve changing a single-phase connection.
A three-phase connection may then be required. The DNO may also need network reinforcement works. The installation may need to wait until these works finish.
The costs of upgrades may differ greatly between properties. The final cost depends on the necessary network work. Your installer should explain any connection charges.
DNO Application Outcomes at a Glance
| DNO outcome | What it means | What happens next? |
|---|---|---|
| Accepted | Requested connection is suitable | Installation can proceed |
| Export limitation | Grid export must stay below a set limit | Installer adds suitable control equipment |
| Supply upgrade | Existing connection lacks capacity | DNO completes required upgrade works |
| Reinforcement required | Wider network changes are needed | Work must finish before connection |
| Revised capacity | Requested capacity cannot be fully supported | Installer adjusts the system design |
Your DNO will confirm the specific conditions. Do not rely on general examples for your property.
Inverter Capacity vs Export Capacity
These two terms are often confused. Inverter capacity is the inverter’s maximum output. Export capacity is the maximum electricity sent to the grid. These figures can be different. For example, consider a 10kW inverter, the DNO might allow only 5kW of export.
Your system can still produce more than 5kW. However, only 5kW can flow into the electricity network. The remaining power can be used on-site or stored. This arrangement can make larger systems possible.
What Is a DNO Letter for Solar Panels?
A DNO letter confirms your connection status. It can confirm approval for an accepted G99 application. It can also confirm relevant connection conditions. For G98, the notification records that your system was notified. The exact document can vary between DNOs.
Homeowners should keep their DNO paperwork safely. You may need it when changing your solar system. You may also need it when selling your property. It can provide evidence of a compliant grid connection.
What Is a DNO Certificate for Solar Panels?
People often use “DNO certificate” as a general term. The actual document name can vary between DNOs. It may refer to an approval, notification, or connection document.
It confirms relevant details about your grid connection. Your installer should provide the appropriate paperwork. Keep this document with your solar installation records.
How Do I Get a DNO Certificate?
Your installer normally handles the DNO process. They submit the required G98 notification or G99 application. The DNO then provides the relevant confirmation.
Ask your installer for a copy after completion. If you cannot find it, contact your DNO. You may need your MPAN and installation details.
How Long Does DNO Approval Take for Solar?
G98 and G99 have different processes. G98 normally does not require approval before installation. The installer submits the notification after commissioning. G99 usually requires approval before installation. The timeframe depends on the application and network conditions.
Complex projects can take considerably longer. Network reinforcement can also extend the project delivery period. Therefore, ask your installer for the current DNO timescale. Never assume every G99 application receives approval immediately.
How Do I Check My DNO Approval?
Start by asking your installer for the necessary documentation, which should include your DNO approval or notification confirmation. Alternatively, you can contact your DNO directly. Give your property information and MPAN if asked. You will find your MPAN on your electricity bill.
Your DNO operator can inform you about the current status of your grid connection. If your application is still pending, ask for the application reference. Your installer should also have the application reference.
Can You Install Solar Without DNO Approval?
This depends on the required connection process. G98 installations usually do not need prior approval. However, they still require DNO notification. G99 installations normally require approval before installation.
Installing a G99 system without approval can create problems. The installed system may not have permission to connect. The DNO may require changes or disconnection. You could also face delays with export arrangements. This is why DNO consent should be checked early.
What Happens If You Skip the DNO Process?
Ignoring the DNO process can cause serious problems. Your solar system may not have an approved grid connection. You may also have problems exporting electricity. This can affect eligibility for export payments.
Your installer may need to correct the connection afterwards. The DNO could require equipment changes or disconnection. Selling your property can also become more complicated.
Buyers can demand evidence of a compliant installation. The insurance conditions can depend on the installation compliance. Always make sure which DNO process to follow before your installation.
Do I Need a DNO Application for Solar Panels or a Battery?
A battery can also require DNO notification or approval. This depends on the battery inverter and connection arrangement. A battery can export electricity to the local network. Therefore, the DNO may need its technical details.
Adding storage later can also change your connection. Always tell your installer about existing battery storage. Also mention any planned future battery installation. The installer can then check the correct G98 or G99 process.
Who Submits the DNO Solar Application?
Your installer normally handles the DNO connection process. They should identify your local DNO. They should also select the correct application route. The installer prepares the technical information.
They then submit the G98 notification or G99 application. You should receive the relevant paperwork afterwards. Always confirm this responsibility before signing your installation contract.
Does a DNO Application Cost Money?
G98 notification is normally a simple process. Your installer may include it within the installation price. G99 applications can involve additional DNO charges. Costs depend on the application and required network work. Export limitation arrangements can also add costs.
Supply upgrades can become considerably more expensive. The DNO should identify applicable charges within its offer. Ask your installer about possible connection costs early. This helps you understand the full solar installation cost.
Can the DNO Limit My Solar System?
Yes, the DNO can impose connection conditions. The most common condition is an export limitation. The DNO may also reduce the approved export capacity. In some cases, network reinforcement may be required.
The decision depends on your local electricity network. This does not mean that your solar installation project is unsuccessful. Your installer can modify your system accordingly.
Can You Reapply for More DNO Capacity?
Yes, you can potentially request more capacity later. Network conditions can change over time. The DNO may complete reinforcement or upgrade local equipment. This could create additional connection capacity.
Your installer can submit a new application. The DNO will then assess the updated proposal. There is no guarantee that additional capacity will be approved. However, a previous restriction may not remain permanent.
DNO Application Checklist for UK Homeowners
Before installing solar panels, check these points:
- Identify your local DNO.
- Ask whether G98 or G99 applies.
- Confirm your inverter capacity.
- Check your proposed export capacity.
- Include battery storage details.
- Ask whether G100 is required.
- Confirm any export limitation.
- Ask about connection charges.
- Check expected approval times.
- Keep your DNO documents.
- Ask about future system expansion.
- Confirm who submits the application.
These steps can prevent unnecessary project delays.
Final Thoughts
A DNO Solar Panel Application is an important part of grid connection. It confirms that your solar system can connect safely. Small systems can often use the simpler G98 route. Larger systems normally require a G99 application. Some systems may also need a G100 export limitation. Your DNO may approve, restrict, or modify your connection.
Your network may also require supply upgrades or network reinforcement. Your installer should handle the whole process. Always check the DNO requirements before you install the solar PV system. It can be useful to keep your DNO documentation to protect yourself for the future. You will need it for upgrades or selling your property. With the proper installer, the DNO process should go smoothly.
FAQs
Neither option is better. G98 suits eligible smaller generating systems. G99 applies to larger or more complex connections. Your installer should determine the correct process.
3.68kW per phase is the commonly used G98 threshold. This corresponds to approximately 16A per phase at 230V. Three-phase systems have different overall connection limits. Always confirm current requirements with your DNO.
Your installer normally submits the required DNO paperwork. The DNO then provides the relevant confirmation. Ask your installer for a copy after commissioning.
A DNO letter confirms relevant connection or notification information. It can provide evidence of your solar grid connection. Keep it with your other installation documents.
G98 normally uses post-installation notification. G99 process can require prior assessment and approval. The time frame varies depending on the project and the network situation. In some cases, complex network reinforcement can take longer.
Ask your installer for the application reference and approval confirmation. Alternatively, you can contact your DNO operator. Your MPAN and property information can help find your application.
Usually, some DNO processes apply to grid-connected equipment. The exact process depends on system capacity and export capability. Your installer should assess both solar and battery equipment.